 After Mold quialification and get shipment approval from customer side, we will do the mold shipment according

 

Some shipment database and document as below (Need check with customer for detail disucssion)

1.Tooling DFM and Mold flow analysis report,

2.Part latest 3d/2d,

3.Tooling 3D/2D layout drawing,

4.Tooling BOM list ,

5.Tooling manufacture plan (weekly update progress),

6.Tooling check list,

7.Tooling trial report & tooling issue tracking list,

8.Tooling FAI report, need combine optimized molding parameter,

9.Tooling CPK report, need combine optimized molding parameter,

10.If need, ask tooling vendor provide Video to show the CPK status,

11.Tooling final check list (onside check by molding vendor),

12.Tooling steel key dimension report,

13.Tooling steel certification , Mold base steel certification,

14.Tooling steel Heat treatment certification,

15.Tooling cavity and core 3d/2d, component 3D/2D, electrode 3D/2D, BOM list all database will be archive into a disk,

16.Hot runner system structure and connection method and spear parts,

17.Tooling maintenance method and key notice,

18.Electrodes collect ,

19.Others like measuring jig, robot jigs, measuring SOT, etc, detail need to discuss,

20.Spare part list. ( free or need buy items)

 